Diesel Generator Solutions Hub
The most comprehensive generator troubleshooting, installation, maintenance & repair guide in East Africa. No one else provides this depth of technical knowledge.
Generator Installation Guide
Complete step-by-step installation procedures from site preparation to commissioning. Following these guidelines ensures safe, reliable operation and warranty compliance.
Site Preparation & Foundation
Step 1 of 6
Survey the installation site for proper ventilation (minimum 1.5m clearance all sides)
⚠️ Critical Step - Do not skipCalculate foundation requirements: Mass = 2× Generator weight minimum
⚠️ Critical Step - Do not skipEnsure concrete curing time: 28 days for full strength, 7 days minimum
Install anti-vibration mounts (AVM) - spring or rubber isolators based on RPM
⚠️ Critical Step - Do not skipVerify floor load capacity: Typically 500-1500 kg/m² for generators
Plan exhaust routing: Maximum 3 bends, proper rain cap, thermal expansion allowance
⚠️ Critical Step - Do not skip💡 Pro Tip: Foundation mass should be 2-5× the generator weight. For 500kVA (3,500kg), foundation should be 7,000-17,500kg concrete.
Electrical Connections
Step 2 of 6
Size cables using IEE regulations: I = P/(√3 × V × PF × Eff) for 3-phase
⚠️ Critical Step - Do not skipInstall properly rated circuit breakers: MCCB at generator, ACB at main panel
⚠️ Critical Step - Do not skipConnect neutral-earth bond at ONE point only (generator or main panel)
⚠️ Critical Step - Do not skipVerify phase sequence (R-Y-B) using phase rotation meter before paralleling
⚠️ Critical Step - Do not skipInstall surge protection devices (SPD) Type 1+2 at generator output
Test insulation resistance: >1MΩ @ 500V DC for LV, >100MΩ for MV
⚠️ Critical Step - Do not skip💡 Pro Tip: Cable sizing formula: Cross-section (mm²) = (1.732 × I × L × ρ) / (ΔV × 1000) where ρ=0.0175 for copper.
Fuel System Installation
Step 3 of 6
Install day tank within 3m of generator, main tank within 30m maximum
Size fuel lines: Minimum 10mm ID for up to 100kVA, 15mm for up to 500kVA
⚠️ Critical Step - Do not skipInstall fuel water separator and primary filter before engine fuel filter
⚠️ Critical Step - Do not skipEnsure return line is larger than supply (prevents vapor lock)
⚠️ Critical Step - Do not skipInstall emergency fuel shutoff valve accessible from outside generator room
⚠️ Critical Step - Do not skipTest fuel system: Prime, check for leaks, verify fuel lift pump pressure (2-5 PSI)
⚠️ Critical Step - Do not skip💡 Pro Tip: Fuel consumption estimate: 0.25-0.30 liters per kWh. A 200kVA @ 80% load ≈ 40 liters/hour.
Cooling System Setup
Step 4 of 6
Calculate radiator airflow: Minimum 8-12 m³/min per 100kW for air-cooled
⚠️ Critical Step - Do not skipInstall remote radiator if needed: Max head 15m, use glycol mix 30-50%
Size ventilation openings: Intake = 0.5 × radiator area, Exhaust = 1.5 × radiator area
⚠️ Critical Step - Do not skipInstall motorized louvers with generator start interlock
Fill coolant: 50% water + 50% ethylene glycol, add DCA4 additive
⚠️ Critical Step - Do not skipPressure test cooling system: 1.0-1.4 bar, check for leaks
⚠️ Critical Step - Do not skip💡 Pro Tip: Room temperature should stay below 40°C. Calculate: Heat rejection (kW) = Rated Power × 0.3 for cooling needs.
Exhaust System Installation
Step 5 of 6
Size exhaust pipe: Minimum equal to engine exhaust outlet, larger for long runs
⚠️ Critical Step - Do not skipInstall flexible connector at engine to absorb vibration (stainless bellows)
⚠️ Critical Step - Do not skipSupport exhaust every 1.5-2m, allow for thermal expansion (10mm per 3m)
⚠️ Critical Step - Do not skipMaintain maximum backpressure: 3-4 kPa for naturally aspirated, 6-7 kPa for turbo
⚠️ Critical Step - Do not skipInstall rain cap and spark arrestor (required for enclosed areas)
Wrap exhaust with insulation in occupied areas (surface temp <60°C)
💡 Pro Tip: Excessive backpressure causes: Power loss (1% per 0.25 kPa over limit), increased fuel consumption, engine damage.
Control Panel & ATS Installation
Step 6 of 6
Mount control panel at eye level, protected from vibration and moisture
Wire all sensors: Oil pressure, water temp, fuel level, battery voltage, RPM pickup
⚠️ Critical Step - Do not skipConfigure ATS: Mains fail delay 5-10s, transfer time <100ms, retransfer delay 5-30min
⚠️ Critical Step - Do not skipSet protection parameters: Overspeed 110%, undervoltage 85%, overcurrent 110%
⚠️ Critical Step - Do not skipTest emergency stop circuit: Must stop engine and disable start
⚠️ Critical Step - Do not skipCommission remote monitoring if required: GSM, Ethernet, Modbus
💡 Pro Tip: DeepSea & PowerWizard controllers: Always backup configuration before commissioning. Use PC software for parameter changes.
Need Expert Help?
Our team of certified generator technicians is available 24/7 for emergency repairs, scheduled maintenance, and technical consultations.